Thames Barrier

flood defence in London

51°29′52″N 0°02′12″E / 51.497744°N 0.036679°E / 51.497744; 0.036679

River Thames Flood Barrier
The gate in the middle of this view has been raised to the maintenance position; a barge can be seen in the foreground.

The Thames Barrier is the world's second-largest movable flood barrier, after the Oosterscheldekering in the Netherlands. It is downstream of central London.[1] Its purpose is to prevent London from being flooded by exceptionally high tides and storm surges moving up from the North Sea. It is raised (closed) only during high tide; at ebb tide it is lowered to release the water which backs up behind it.

The barrier's northern bank is in the London Borough of Newham and its southern bank is in the London Borough of Greenwich. The report of Hermann Bondi into the North Sea flood of 1953 affecting parts of the Thames Estuary and parts of London was what led to the building of the barrier.[2][3]

Geography change

Geographical weather system change

London is vulnerable to flooding. A storm surge generated by low pressure in the Atlantic Ocean sometimes tracks eastwards past the north of Scotland and may then be driven into the shallow waters of the North Sea. The surge tide is funnelled down the North Sea which narrows towards the English Channel and the Thames Estuary. If the storm surge coincides with a spring tide, dangerously high water levels can occur in the Thames Estuary. This situation combined with downstream flows in the Thames tells engineers when to operate the barriers.

Rising water levels change

The threat has increased over time due to the slow but continuous rise in high water level over the centuries (20 cm (8 inches) / 100 years) and the slow "tilting" of Britain (up in the north and west, and down in the south and east) caused by post-glacial rebound.[4]

Historical flooding change

Fourteen people died in the 1928 Thames flood, and after 307 people died in the UK in the North Sea Flood of 1953 the issue gained new prominence.

Early proposals for a flood control system were stymied by the need for a large opening in the barrier to allow for vessels from London Docks to pass through. When containerization replaced older forms of shipping and a new port was opened at Tilbury, a smaller barrier became feasible with each of the four main navigation spans being the same width as the opening of Tower Bridge.

The barrier from Silvertown on the north bank of the river during normal operation looking across to New Charlton.

Operation change

 
Underground tunnel between Thames Barrier piers.

A Thames Barrier flood defence closure is triggered when high tides are forecast in the North Sea and river flows are high at the tidal limit at Teddington weir.[5] If water levels might exceed 4.87 metres (16.0 ft) in central London, that is the trigger.

Closure begins about 9 hours before a dangerous high tide reaches the barrier. Messages give orders to stop river traffic, close subsidiary gates and alert other river users. As well as the Thames Barrier, the smaller gates along the Thames Tideway must be closed. Once river navigation has been stopped and all gates closed, then the Thames Barrier itself can be closed. The smaller gates are closed first, then the main navigable spans in succession. The gates remain closed until the tide downstream of the barrier falls to the same level as the water level upstream.

After heavy rain west of London, floodwater flows down the Thames upstream (before London). Because the river is tidal from Teddington weir all the way through London, this is only a problem at high tide, which prevents the floodwater from escaping out to sea. From Teddington the river is opening out into its estuary, and at low tide it can take much greater flow rates the further one goes downstream.

When the river is in flood upstream, if the gates are closed shortly after low tide, a huge empty volume holds behind the barrier which can act as a reservoir to hold the floodwater coming over Teddington weir. Most river floods will not fill this volume in the few high tide hours when the barrier needs to be closed. If the barrier was not there, the high tide would fill up this volume instead, and the floodwater could then spill over the river banks in London. About a third of the closures up to 2009 were to prevent flooding caused by heavy rain to the west of London.

Closures and incidents change

In the 1980s there were four closures, 35 closures in the 1990s, and 75 closures in the first decade of this century.[6] The rate of closures is above that predicted, and is increasing rapidly.

An incident that was potentially catastrophic for London occurred on 27 October 1997. The dredger, MV Sand Kite, sailing in thick fog, collided with one of the Thames Barrier's piers. As the ship started to sink she dumped her 3,300 tonne load of aggregate, finally sinking by the bow on top of one of the barrier's gates where she lay for several days. Initially the gate could not be closed as it was covered in a thick layer of gravel. A longer term problem was the premature loss of paint on the flat side of the gate caused by abrasion. One estimate of the cost of flooding damage, had it occurred, was around £13 billion.[7] The vessel was refloated in mid-November 1997.

The barrier was closed twice on 9 November 2007 after a storm surge in the North Sea which was compared to the one in 1953.[8] The main danger of flooding from the surge was on the coast above the Thames Barrier, where evacuations took place, but the winds abated a little and, at the Thames Barrier, the 9 November 2007 storm surge did not completely coincide with high tide.[9]

Future change

The barrier was originally designed to protect London against a big flood level.[10] The defence level included long-term changes in sea and land levels as understood at that time (~1970). Despite global warming, and a higher predicted rate of sea level rise, recent analysis suggested the barrier could last until around 2060–2070.[11]

Released in 2005, a study by four respected academics contained a proposal to replace the Thames Barrier with a more ambitious 16 km (10 mi) long barrier across the Thames Estuary from Sheerness in Kent to Southend in Essex.[12]

References change

  1. Downstream = towards the sea; in this case, east of London towards the Thames estuary.
  2. "1953 floods in Canning Town, Accessed 30 December 2010" (PDF). Archived from the original (PDF) on 20 November 2008. Retrieved 6 September 2011.
  3. "Bondi, Sir Hermann (1919–2005), applied mathematician and scientific administrator". Oxford Dictionary of National Biography (online ed.). Oxford University Press. doi:10.1093/ref:odnb/96022. ISBN 978-0-19-861412-8. (Subscription or UK public library membership required.)
  4. At the end of the ice age, the three-mile thick ice sheet over Britain north of the Thames melted. The northern part of Britain, previously pressed down by the ice, rose up. This tilted the land mass, and the southern part of south-east England tilted down as a result of the northern rise. This movement continues at a very slow pace.
  5. Teddington weir is part of a complex of three locks and a weir on the river at Teddington, west London.
  6. The Environmental Agency (2010). "Thames Barrier closures – indicator two". web page. Environmental Agency. Archived from the original on 3 April 2011. Retrieved 20 April 2010.
  7. "Contact made by dredger/sand carrier Sand Kite with Thames Flood Barrier resulting in flooding and partial sinking of vessel". GOV.UK.
  8. BBC report, accessed 8 December 2007
  9. Surge of 9 November 2007-11-09 Archived 2012-02-21 at the Wayback Machine The Proudman Oceanographic Laboratory (POL), (a part of the Natural Environment Research Council)
  10. "Archived copy". Archived from the original on 2009-06-06. Retrieved 2011-09-06.{{cite web}}: CS1 maint: archived copy as title (link)
  11. "ThamesWeb". Archived from the original on 2008-12-23. Retrieved 2011-09-06.
  12. Times Online January 9, 2005